Categorías | Tarifas Reguladas 2025 | Cargos variables | enero-25 | |||||
Transmisión | Distribución | Operación del CENACE | Operación del Suministrador Básico | Servicios conexos no MEM | Energía | Capacidad | ||
Categoría tarifaria | Unidades | |||||||
DB1 | $/mes | | | | 78.29 | | | |
| $/kWh | 0.1809 | 0.7635 | 0.0065 | | 0.0062 | 0.652 | 0.497 |
DB2 | $/mes | | | | 78.29 | | | |
| $/kWh | 0.1809 | 0.8697 | 0.0065 | | 0.0062 | 0.652 | 0.495 |
PDBT | $/mes | | | | 78.29 | | | |
| $/kWh | 0.1809 | 0.6985 | 0.0065 | | 0.0062 | 0.705 | 1.067 |
| $/mes | | | | 782.90 | | | |
GDBT | $/kWh | 0.1809 | | 0.0065 | | 0.0062 | 0.714 | |
| $/kW | | 201.73 | | | | | 334.71 |
RABT | $/mes | | | | 78.29 | | | |
| $/kWh | 0.1809 | 0.6985 | 0.0065 | | 0.0062 | 0.651 | 0.569 |
| $/mes | | | | 782.90 | | | |
RAMT | $/kWh | 0.1809 | | 0.0065 | | 0.0062 | 0.642 | |
| $/kW | | 93.86 | | | | | 165.68 |
APBT | $/mes | | | | 78.29 | | | |
| $/kWh | 0.1809 | 0.6985 | 0.0065 | | 0.0062 | 0.587 | 1.483 |
| $/mes | | | | 782.90 | | | |
APMT | $/kWh | 0.1809 | | 0.0065 | | 0.0062 | 0.504 | 1.219 |
| $/kW | | 93.86 | | | | | |
| $/mes | | | | 782.90 | | | |
GDMTO | $/kWh | 0.1809 | | 0.0065 | | 0.0062 | 0.557 | |
| $/kW | | 93.86 | | | | | 366.47 |
| $/mes | | | | 782.90 | | | |
| $/kWh Base | 0.1809 | | 0.0065 | | 0.0062 | 0.4490 | |
GDMTH | $/kWh Intermedio | 0.1809 | | 0.0065 | | 0.0062 | 0.8129 | |
| $/kWh Punta | 0.1809 | | 0.0065 | | 0.0062 | 1.1704 | |
| $/kW | | 93.86 | | | | | 384.70 |
| $/mes | | | | 2348.70 | | | |
| $/kWh Base | 0.1809 | | 0.0065 | | 0.0062 | 0.4905 | |
DIST | $/kWh Intermedio | 0.1809 | | 0.0065 | | 0.0062 | 0.8882 | |
| $/kWh Punta | 0.1809 | | 0.0065 | | 0.0062 | 1.2802 | |
| $/kWh Semipunta | 0.1809 | | 0.0065 | | 0.0062 | 1.2018 | |
| $/kW | | | | | | | 421.46 |
| $/mes | | | | 2348.70 | | | |
| $/kWh Base | 0.0794 | | 0.0065 | | 0.0062 | 0.5671 | |
DIT | $/kWh Intermedio | 0.0794 | | 0.0065 | | 0.0062 | 1.0268 | |
| $/kWh Punta | 0.0794 | | 0.0065 | | 0.0062 | 1.4753 | |
| $/kWh Semipunta | 0.0794 | | 0.0065 | | 0.0062 | 1.3856 | |
| $/kW | | | | | | | 431.76 |
Categorías | Tarifas Reguladas 2025 | Cargos variables | enero-25 | |||||
Transmisión | Distribución | Operación del CENACE | Operación del Suministrador Básico | Servicios conexos no MEM | Energía | Capacidad | ||
Categoría tarifaria | Unidades | |||||||
DB1 | $/mes | | | | 78.29 | | | |
| $/kWh | 0.1809 | 0.7635 | 0.0065 | | 0.0062 | 0.932 | 0.497 |
DB2 | $/mes | | | | 78.29 | | | |
| $/kWh | 0.1809 | 0.8697 | 0.0065 | | 0.0062 | 0.930 | 0.495 |
PDBT | $/mes | | | | 78.29 | | | |
| $/kWh | 0.1809 | 0.6985 | 0.0065 | | 0.0062 | 2.526 | 0.757 |
| $/mes | | | | 782.90 | | | |
GDBT | $/kWh | 0.1809 | | 0.0065 | | 0.0062 | 3.042 | |
| $/kW | | 201.73 | | | | | 284.32 |
RABT | $/mes | | | | 78.29 | | | |
| $/kWh | 0.1809 | 0.6985 | 0.0065 | | 0.0062 | 0.929 | 0.569 |
| $/mes | | | | 782.90 | | | |
RAMT | $/kWh | 0.1809 | | 0.0065 | | 0.0062 | 0.886 | |
| $/kW | | 93.86 | | | | | 165.68 |
APBT | $/mes | | | | 78.29 | | | |
| $/kWh | 0.1809 | 0.6985 | 0.0065 | | 0.0062 | 3.134 | 1.378 |
| $/mes | | | | 782.90 | | | |
APMT | $/kWh | 0.1809 | | 0.0065 | | 0.0062 | 2.107 | 0.874 |
| $/kW | | 93.86 | | | | | |
| $/mes | | | | 782.90 | | | |
GDMTO | $/kWh | 0.1809 | | 0.0065 | | 0.0062 | 2.302 | |
| $/kW | | 93.86 | | | | | 281.79 |
| $/mes | | | | 782.90 | | | |
| $/kWh Base | 0.1809 | | 0.0065 | | 0.0062 | 2.0442 | |
GDMTH | $/kWh Intermedio | 0.1809 | | 0.0065 | | 0.0062 | 2.6520 | |
| $/kWh Punta | 0.1809 | | 0.0065 | | 0.0062 | 3.8183 | |
| $/kW | | 93.86 | | | | | 275.76 |
| $/mes | | | | 2348.70 | | | |
| $/kWh Base | 0.1809 | | 0.0065 | | 0.0062 | 2.2289 | |
DIST | $/kWh Intermedio | 0.1809 | | 0.0065 | | 0.0062 | 2.8915 | |
| $/kWh Punta | 0.1809 | | 0.0065 | | 0.0062 | 4.1679 | |
| $/kW | | | | | | | 307.52 |
| $/mes | | | | 2348.70 | | | |
| $/kWh Base | 0.0794 | | 0.0065 | | 0.0062 | 2.6079 | |
DIT | $/kWh Intermedio | 0.0794 | | 0.0065 | | 0.0062 | 3.2892 | |
| $/kWh Punta | 0.0794 | | 0.0065 | | 0.0062 | 4.7258 | |
| $/kW | | | | | | | 357.20 |
Categorías | Tarifas Reguladas 2025 | Cargos variables | enero-25 | |||||
Transmisión | Distribución | Operación del CENACE | Operación del Suministrador Básico | Servicios conexos no MEM | Energía | Capacidad | ||
Categoría tarifaria | Unidades | |||||||
DB1 | $/mes | | | | 36.89 | | | |
| $/kWh | 0.1809 | 1.1925 | 0.0065 | | 0.0062 | 0.845 | 0.547 |
DB2 | $/mes | | | | 36.89 | | | |
| $/kWh | 0.1809 | 1.0220 | 0.0065 | | 0.0062 | 0.841 | 0.544 |
PDBT | $/mes | | | | 36.89 | | | |
| $/kWh | 0.1809 | 0.9722 | 0.0065 | | 0.0062 | 1.761 | 1.135 |
| $/mes | | | | 368.95 | | | |
GDBT | $/kWh | 0.1809 | | 0.0065 | | 0.0062 | 1.779 | |
| $/kW | | 386.09 | | | | | 326.70 |
RABT | $/mes | | | | 36.89 | | | |
| $/kWh | 0.1809 | 0.9722 | 0.0065 | | 0.0062 | 0.824 | 0.630 |
| $/mes | | | | 368.95 | | | |
RAMT | $/kWh | 0.1809 | | 0.0065 | | 0.0062 | 0.780 | |
| $/kW | | 102.05 | | | | | 165.68 |
APBT | $/mes | | | | 36.89 | | | |
| $/kWh | 0.1809 | 0.9722 | 0.0065 | | 0.0062 | 1.566 | 1.643 |
| $/mes | | | | 368.95 | | | |
APMT | $/kWh | 0.1809 | | 0.0065 | | 0.0062 | 1.262 | 1.240 |
| $/kW | | 102.05 | | | | | |
| $/mes | | | | 368.95 | | | |
GDMTO | $/kWh | 0.1809 | | 0.0065 | | 0.0062 | 1.444 | |
| $/kW | | 102.05 | | | | | 362.82 |
| $/mes | | | | 368.95 | | | |
| $/kWh Base | 0.1809 | | 0.0065 | | 0.0062 | 0.9254 | |
GDMTH | $/kWh Intermedio | 0.1809 | | 0.0065 | | 0.0062 | 1.8059 | |
| $/kWh Punta | 0.1809 | | 0.0065 | | 0.0062 | 2.0867 | |
| $/kW | | 102.05 | | | | | 421.46 |
| $/mes | | | | 1106.85 | | | |
| $/kWh Base | 0.1809 | | 0.0065 | | 0.0062 | 0.9687 | |
DIST | $/kWh Intermedio | 0.1809 | | 0.0065 | | 0.0062 | 1.7164 | |
| $/kWh Punta | 0.1809 | | 0.0065 | | 0.0062 | 2.0749 | |
| $/kW | | | | | | | 431.76 |
| $/mes | | | | 1106.85 | | | |
| $/kWh Base | 0.0794 | | 0.0065 | | 0.0062 | 0.8318 | |
DIT | $/kWh Intermedio | 0.0794 | | 0.0065 | | 0.0062 | 1.6259 | |
| $/kWh Punta | 0.0794 | | 0.0065 | | 0.0062 | 1.8084 | |
| $/kW | | | | | | | 431.76 |
Categorías | Tarifas Reguladas 2025 | Cargos variables | enero-25 | |||||
Transmisión | Distribución | Operación del CENACE | Operación del Suministrador Básico | Servicios conexos no MEM | Energía | Capacidad | ||
Categoría tarifaria | Unidades | |||||||
DB1 | $/mes | | | | 24.53 | | | |
| $/kWh | 0.1809 | 1.6047 | 0.0065 | | 0.0062 | 0.812 | 0.486 |
DB2 | $/mes | | | | 24.53 | | | |
| $/kWh | 0.1809 | 1.3754 | 0.0065 | | 0.0062 | 0.813 | 0.484 |
PDBT | $/mes | | | | 24.53 | | | |
| $/kWh | 0.1809 | 1.3076 | 0.0065 | | 0.0062 | 1.534 | 0.939 |
| $/mes | | | | 245.25 | | | |
GDBT | $/kWh | 0.1809 | | 0.0065 | | 0.0062 | 1.350 | |
| $/kW | | 518.12 | | | | | 279.50 |
RABT | $/mes | | | | 24.53 | | | |
| $/kWh | 0.1809 | 1.3076 | 0.0065 | | 0.0062 | 0.803 | 0.555 |
| $/mes | | | | 245.25 | | | |
RAMT | $/kWh | 0.1809 | | 0.0065 | | 0.0062 | 0.779 | |
| $/kW | | 162.01 | | | | | 165.68 |
APBT | $/mes | | | | 24.53 | | | |
| $/kWh | 0.1809 | 1.3076 | 0.0065 | | 0.0062 | 1.429 | 1.447 |
| $/mes | | | | 245.25 | | | |
APMT | $/kWh | 0.1809 | | 0.0065 | | 0.0062 | 1.263 | 1.228 |
| $/kW | | 162.01 | | | | | |
| $/mes | | | | 245.25 | | | |
GDMTO | $/kWh | 0.1809 | | 0.0065 | | 0.0062 | 1.291 | |
| $/kW | | 162.01 | | | | | 319.71 |
| $/mes | | | | 245.25 | | | |
| $/kWh Base | 0.1809 | | 0.0065 | | 0.0062 | 0.9230 | |
GDMTH | $/kWh Intermedio | 0.1809 | | 0.0065 | | 0.0062 | 1.8087 | |
| $/kWh Punta | 0.1809 | | 0.0065 | | 0.0062 | 2.0635 | |
| $/kW | | 162.01 | | | | | 421.29 |
| $/mes | | | | 735.76 | | | |
| $/kWh Base | 0.1809 | | 0.0065 | | 0.0062 | 0.9271 | |
DIST | $/kWh Intermedio | 0.1809 | | 0.0065 | | 0.0062 | 1.6495 | |
| $/kWh Punta | 0.1809 | | 0.0065 | | 0.0062 | 1.9790 | |
| $/kW | | | | | | | 431.76 |
| $/mes | | | | 735.76 | | | |
| $/kWh Base | 0.0794 | | 0.0065 | | 0.0062 | 0.8726 | |
DIT | $/kWh Intermedio | 0.0794 | | 0.0065 | | 0.0062 | 1.6280 | |
| $/kWh Punta | 0.0794 | | 0.0065 | | 0.0062 | 1.8389 | |
| $/kW | | | | | | | 431.76 |
Categorías | Tarifas Reguladas 2025 | Cargos variables | enero-25 | |||||
Transmisión | Distribución | Operación del CENACE | Operación del Suministrador Básico | Servicios conexos no MEM | Energía | Capacidad | ||
Categoría tarifaria | Unidades | |||||||
DB1 | $/mes | | | | 30.81 | | | |
| $/kWh | 0.1809 | 1.4928 | 0.0065 | | 0.0062 | 0.837 | 0.536 |
DB2 | $/mes | | | | 30.81 | | | |
| $/kWh | 0.1809 | 1.2799 | 0.0065 | | 0.0062 | 0.840 | 0.533 |
PDBT | $/mes | | | | 30.81 | | | |
| $/kWh | 0.1809 | 1.2161 | 0.0065 | | 0.0062 | 1.529 | 0.943 |
| $/mes | | | | 308.10 | | | |
GDBT | $/kWh | 0.1809 | | 0.0065 | | 0.0062 | 1.602 | |
| $/kW | | 482.02 | | | | | 294.06 |
RABT | $/mes | | | | 30.81 | | | |
| $/kWh | 0.1809 | 1.2161 | 0.0065 | | 0.0062 | 0.818 | 0.617 |
| $/mes | | | | 308.10 | | | |
RAMT | $/kWh | 0.1809 | | 0.0065 | | 0.0062 | 0.778 | |
| $/kW | | 155.81 | | | | | 165.68 |
APBT | $/mes | | | | 30.81 | | | |
| $/kWh | 0.1809 | 1.2161 | 0.0065 | | 0.0062 | 1.540 | 1.608 |
| $/mes | | | | 308.10 | | | |
APMT | $/kWh | 0.1809 | | 0.0065 | | 0.0062 | 1.259 | 1.233 |
| $/kW | | 155.81 | | | | | |
| $/mes | | | | 308.10 | | | |
GDMTO | $/kWh | 0.1809 | | 0.0065 | | 0.0062 | 1.423 | |
| $/kW | | 155.81 | | | | | 359.79 |
| $/mes | | | | 308.10 | | | |
| $/kWh Base | 0.1809 | | 0.0065 | | 0.0062 | 0.9202 | |
GDMTH | $/kWh Intermedio | 0.1809 | | 0.0065 | | 0.0062 | 1.8097 | |
| $/kWh Punta | 0.1809 | | 0.0065 | | 0.0062 | 2.0695 | |
| $/kW | | 155.81 | | | | | 417.55 |
| $/mes | | | | 924.29 | | | |
| $/kWh Base | 0.1809 | | 0.0065 | | 0.0062 | 0.9099 | |
DIST | $/kWh Intermedio | 0.1809 | | 0.0065 | | 0.0062 | 1.6932 | |
| $/kWh Punta | 0.1809 | | 0.0065 | | 0.0062 | 1.9363 | |
| $/kW | | | | | | | 431.76 |
| $/mes | | | | 924.29 | | | |
| $/kWh Base | 0.0794 | | 0.0065 | | 0.0062 | 0.9258 | |
DIT | $/kWh Intermedio | 0.0794 | | 0.0065 | | 0.0062 | 1.6529 | |
| $/kWh Punta | 0.0794 | | 0.0065 | | 0.0062 | 1.9726 | |
| $/kW | | | | | | | 431.76 |
Categorías | Tarifas Reguladas 2025 | Cargos variables | enero-25 | |||||
Transmisión | Distribución | Operación del CENACE | Operación del Suministrador Básico | Servicios conexos no MEM | Energía | Capacidad | ||
Categoría tarifaria | Unidades | |||||||
DB1 | $/mes | | | | 28.97 | | | |
| $/kWh | 0.1809 | 1.6840 | 0.0065 | | 0.0062 | 0.853 | 0.580 |
DB2 | $/mes | | | | 28.97 | | | |
| $/kWh | 0.1809 | 1.4425 | 0.0065 | | 0.0062 | 0.843 | 0.577 |
PDBT | $/mes | | | | 28.97 | | | |
| $/kWh | 0.1809 | 1.3720 | 0.0065 | | 0.0062 | 1.430 | 0.933 |
| $/mes | | | | 289.74 | | | |
GDBT | $/kWh | 0.1809 | | 0.0065 | | 0.0062 | 1.449 | |
| $/kW | | 543.74 | | | | | 259.76 |
RABT | $/mes | | | | 28.97 | | | |
| $/kWh | 0.1809 | 1.3720 | 0.0065 | | 0.0062 | 0.841 | 0.671 |
| $/mes | | | | 289.74 | | | |
RAMT | $/kWh | 0.1809 | | 0.0065 | | 0.0062 | 0.785 | |
| $/kW | | 230.35 | | | | | 165.68 |
APBT | $/mes | | | | 28.97 | | | |
| $/kWh | 0.1809 | 1.3720 | 0.0065 | | 0.0062 | 1.692 | 1.750 |
| $/mes | | | | 289.74 | | | |
APMT | $/kWh | 0.1809 | | 0.0065 | | 0.0062 | 0.986 | 1.024 |
| $/kW | | 230.35 | | | | | |
| $/mes | | | | 289.74 | | | |
GDMTO | $/kWh | 0.1809 | | 0.0065 | | 0.0062 | 1.152 | |
| $/kW | | 230.35 | | | | | 282.16 |
| $/mes | | | | 289.74 | | | |
| $/kWh Base | 0.1809 | | 0.0065 | | 0.0062 | 0.8294 | |
GDMTH | $/kWh Intermedio | 0.1809 | | 0.0065 | | 0.0062 | 1.6246 | |
| $/kWh Punta | 0.1809 | | 0.0065 | | 0.0062 | 1.8664 | |
| $/kW | | 230.35 | | | | | 392.11 |
| $/mes | | | | 869.22 | | | |
| $/kWh Base | 0.1809 | | 0.0065 | | 0.0062 | 0.9571 | |
DIST | $/kWh Intermedio | 0.1809 | | 0.0065 | | 0.0062 | 1.7143 | |
| $/kWh Punta | 0.1809 | | 0.0065 | | 0.0062 | 2.0380 | |
| $/kW | | | | | | | 431.76 |
| $/mes | | | | 869.22 | | | |
| $/kWh Base | 0.0794 | | 0.0065 | | 0.0062 | 0.9957 | |
DIT | $/kWh Intermedio | 0.0794 | | 0.0065 | | 0.0062 | 1.7790 | |
| $/kWh Punta | 0.0794 | | 0.0065 | | 0.0062 | 2.1041 | |
| $/kW | | | | | | | 431.76 |
Categorías | Tarifas Reguladas 2025 | Cargos variables | enero-25 | |||||
Transmisión | Distribución | Operación del CENACE | Operación del Suministrador Básico | Servicios conexos no MEM | Energía | Capacidad | ||
Categoría tarifaria | Unidades | |||||||
DB1 | $/mes | | | | 34.40 | | | |
| $/kWh | 0.1809 | 1.1640 | 0.0065 | | 0.0062 | 0.798 | 0.508 |
DB2 | $/mes | | | | 34.40 | | | |
| $/kWh | 0.1809 | 0.9424 | 0.0065 | | 0.0062 | 0.802 | 0.505 |
PDBT | $/mes | | | | 34.40 | | | |
| $/kWh | 0.1809 | 1.1684 | 0.0065 | | 0.0062 | 1.736 | 1.090 |
| $/mes | | | | 343.99 | | | |
GDBT | $/kWh | 0.1809 | | 0.0065 | | 0.0062 | 1.583 | |
| $/kW | | 393.20 | | | | | 326.70 |
RABT | $/mes | | | | 34.40 | | | |
| $/kWh | 0.1809 | 1.1684 | 0.0065 | | 0.0062 | 0.797 | 0.582 |
| $/mes | | | | 343.99 | | | |
RAMT | $/kWh | 0.1809 | | 0.0065 | | 0.0062 | 0.768 | |
| $/kW | | 130.04 | | | | | 165.68 |
APBT | $/mes | | | | 34.40 | | | |
| $/kWh | 0.1809 | 1.1684 | 0.0065 | | 0.0062 | 1.365 | 1.517 |
| $/mes | | | | 343.99 | | | |
APMT | $/kWh | 0.1809 | | 0.0065 | | 0.0062 | 1.167 | 1.230 |
| $/kW | | 130.04 | | | | | |
| $/mes | | | | 343.99 | | | |
GDMTO | $/kWh | 0.1809 | | 0.0065 | | 0.0062 | 1.248 | |
| $/kW | | 130.04 | | | | | 344.99 |
| $/mes | | | | 343.99 | | | |
| $/kWh Base | 0.1809 | | 0.0065 | | 0.0062 | 0.8668 | |
GDMTH | $/kWh Intermedio | 0.1809 | | 0.0065 | | 0.0062 | 1.6104 | |
| $/kWh Punta | 0.1809 | | 0.0065 | | 0.0062 | 1.8994 | |
| $/kW | | 130.04 | | | | | 421.46 |
| $/mes | | | | 1031.98 | | | |
| $/kWh Base | 0.1809 | | 0.0065 | | 0.0062 | 0.8957 | |
DIST | $/kWh Intermedio | 0.1809 | | 0.0065 | | 0.0062 | 1.5654 | |
| $/kWh Punta | 0.1809 | | 0.0065 | | 0.0062 | 1.7936 | |
| $/kW | | | | | | | 431.76 |
| $/mes | | | | 1031.98 | | | |
| $/kWh Base | 0.0794 | | 0.0065 | | 0.0062 | 0.9475 | |
DIT | $/kWh Intermedio | 0.0794 | | 0.0065 | | 0.0062 | 1.7580 | |
| $/kWh Punta | 0.0794 | | 0.0065 | | 0.0062 | 1.9258 | |
| $/kW | | | | | | | 431.76 |
Categorías | Tarifas Reguladas 2025 | Cargos variables | enero-25 | |||||
Transmisión | Distribución | Operación del CENACE | Operación del Suministrador Básico | Servicios conexos no MEM | Energía | Capacidad | ||
Categoría tarifaria | Unidades | |||||||
DB1 | $/mes | | | | 55.18 | | | |
| $/kWh | 0.1809 | 0.8438 | 0.0065 | | 0.0062 | 0.781 | 0.547 |
DB2 | $/mes | | | | 55.18 | | | |
| $/kWh | 0.1809 | 0.6835 | 0.0065 | | 0.0062 | 0.781 | 0.545 |
PDBT | $/mes | | | | 55.18 | | | |
| $/kWh | 0.1809 | 0.8474 | 0.0065 | | 0.0062 | 1.531 | 1.176 |
| $/mes | | | | 551.77 | | | |
GDBT | $/kWh | 0.1809 | | 0.0065 | | 0.0062 | 1.279 | |
| $/kW | | 285.03 | | | | | 286.77 |
RABT | $/mes | | | | 55.18 | | | |
| $/kWh | 0.1809 | 0.8474 | 0.0065 | | 0.0062 | 0.780 | 0.632 |
| $/mes | | | | 551.77 | | | |
RAMT | $/kWh | 0.1809 | | 0.0065 | | 0.0062 | 0.743 | |
| $/kW | | 60.23 | | | | | 165.68 |
APBT | $/mes | | | | 55.18 | | | |
| $/kWh | 0.1809 | 0.8474 | 0.0065 | | 0.0062 | 1.278 | 1.646 |
| $/mes | | | | 551.77 | | | |
APMT | $/kWh | 0.1809 | | 0.0065 | | 0.0062 | 1.021 | 1.220 |
| $/kW | | 60.23 | | | | | |
| $/mes | | | | 551.77 | | | |
GDMTO | $/kWh | 0.1809 | | 0.0065 | | 0.0062 | 1.152 | |
| $/kW | | 60.23 | | | | | 366.47 |
| $/mes | | | | 551.77 | | | |
| $/kWh Base | 0.1809 | | 0.0065 | | 0.0062 | 0.8893 | |
GDMTH | $/kWh Intermedio | 0.1809 | | 0.0065 | | 0.0062 | 1.4960 | |
| $/kWh Punta | 0.1809 | | 0.0065 | | 0.0062 | 1.6413 | |
| $/kW | | 60.23 | | | | | 431.76 |
| $/mes | | | | 1655.31 | | | |
| $/kWh Base | 0.1809 | | 0.0065 | | 0.0062 | 0.8629 | |
DIST | $/kWh Intermedio | 0.1809 | | 0.0065 | | 0.0062 | 1.4724 | |
| $/kWh Punta | 0.1809 | | 0.0065 | | 0.0062 | 1.6158 | |
| $/kW | | | | | | | 431.76 |
| $/mes | | | | 1655.31 | | | |
| $/kWh Base | 0.0794 | | 0.0065 | | 0.0062 | 0.7737 | |
DIT | $/kWh Intermedio | 0.0794 | | 0.0065 | | 0.0062 | 1.4267 | |
| $/kWh Punta | 0.0794 | | 0.0065 | | 0.0062 | 1.5034 | |
| $/kW | | | | | | | 431.76 |
Categorías | Tarifas Reguladas 2025 | Cargos variables | enero-25 | |||||
Transmisión | Distribución | Operación del CENACE | Operación del Suministrador Básico | Servicios conexos no MEM | Energía | Capacidad | ||
Categoría tarifaria | Unidades | |||||||
DB1 | $/mes | | | | 37.24 | | | |
| $/kWh | 0.1809 | 1.7114 | 0.0065 | | 0.0062 | 0.838 | 0.540 |
DB2 | $/mes | | | | 37.24 | | | |
| $/kWh | 0.1809 | 1.4668 | 0.0065 | | 0.0062 | 0.840 | 0.538 |
PDBT | $/mes | | | | 37.24 | | | |
| $/kWh | 0.1809 | 1.3951 | 0.0065 | | 0.0062 | 1.882 | 1.161 |
| $/mes | | | | 372.38 | | | |
GDBT | $/kWh | 0.1809 | | 0.0065 | | 0.0062 | 1.400 | |
| $/kW | | 552.46 | | | | | 262.37 |
RABT | $/mes | | | | 37.24 | | | |
| $/kWh | 0.1809 | 1.3951 | 0.0065 | | 0.0062 | 0.826 | 0.623 |
| $/mes | | | | 372.38 | | | |
RAMT | $/kWh | 0.1809 | | 0.0065 | | 0.0062 | 0.782 | |
| $/kW | | 167.07 | | | | | 165.68 |
APBT | $/mes | | | | 37.24 | | | |
| $/kWh | 0.1809 | 1.3951 | 0.0065 | | 0.0062 | 1.583 | 1.622 |
| $/mes | | | | 372.38 | | | |
APMT | $/kWh | 0.1809 | | 0.0065 | | 0.0062 | 1.275 | 1.221 |
| $/kW | | 167.07 | | | | | |
| $/mes | | | | 372.38 | | | |
GDMTO | $/kWh | 0.1809 | | 0.0065 | | 0.0062 | 1.312 | |
| $/kW | | 167.07 | | | | | 334.76 |
| $/mes | | | | 372.38 | | | |
| $/kWh Base | 0.1809 | | 0.0065 | | 0.0062 | 0.8814 | |
GDMTH | $/kWh Intermedio | 0.1809 | | 0.0065 | | 0.0062 | 1.7374 | |
| $/kWh Punta | 0.1809 | | 0.0065 | | 0.0062 | 1.9811 | |
| $/kW | | 167.07 | | | | | 421.46 |
| $/mes | | | | 1117.15 | | | |
| $/kWh Base | 0.1809 | | 0.0065 | | 0.0062 | 0.9489 | |
DIST | $/kWh Intermedio | 0.1809 | | 0.0065 | | 0.0062 | 1.6941 | |
| $/kWh Punta | 0.1809 | | 0.0065 | | 0.0062 | 2.0397 | |
| $/kW | | | | | | | 431.76 |
| $/mes | | | | 1117.15 | | | |
| $/kWh Base | 0.0794 | | 0.0065 | | 0.0062 | 0.8477 | |
DIT | $/kWh Intermedio | 0.0794 | | 0.0065 | | 0.0062 | 1.6321 | |
| $/kWh Punta | 0.0794 | | 0.0065 | | 0.0062 | 1.8674 | |
| $/kW | | | | | | | 421.46 |
Categorías | Tarifas Reguladas 2025 | Cargos variables | enero-25 | |||||
Transmisión | Distribución | Operación del CENACE | Operación del Suministrador Básico | Servicios conexos no MEM | Energía | Capacidad | ||
Categoría tarifaria | Unidades | |||||||
DB1 | $/mes | | | | 77.77 | | | |
| $/kWh | 0.1809 | 0.9381 | 0.0065 | | 0.0062 | 0.762 | 0.495 |
DB2 | $/mes | | | | 77.77 | | | |
| $/kWh | 0.1809 | 0.7413 | 0.0065 | | 0.0062 | 0.762 | 0.493 |
PDBT | $/mes | | | | 77.77 | | | |
| $/kWh | 0.1809 | 0.8072 | 0.0065 | | 0.0062 | 1.489 | 1.063 |
| $/mes | | | | 777.67 | | | |
GDBT | $/kWh | 0.1809 | | 0.0065 | | 0.0062 | 1.430 | |
| $/kW | | 222.11 | | | | | 334.71 |
RABT | $/mes | | | | 77.77 | | | |
| $/kWh | 0.1809 | 0.8072 | 0.0065 | | 0.0062 | 0.759 | 0.567 |
| $/mes | | | | 777.67 | | | |
RAMT | $/kWh | 0.1809 | | 0.0065 | | 0.0062 | 0.738 | |
| $/kW | | 94.64 | | | | | 165.68 |
APBT | $/mes | | | | 77.77 | | | |
| $/kWh | 0.1809 | 0.8072 | 0.0065 | | 0.0062 | 1.262 | 1.477 |
| $/mes | | | | 777.67 | | | |
APMT | $/kWh | 0.1809 | | 0.0065 | | 0.0062 | 1.092 | 1.224 |
| $/kW | | 94.64 | | | | | |
| $/mes | | | | 777.67 | | | |
GDMTO | $/kWh | 0.1809 | | 0.0065 | | 0.0062 | 1.191 | |
| $/kW | | 94.64 | | | | | 366.47 |
| $/mes | | | | 777.67 | | | |
| $/kWh Base | 0.1809 | | 0.0065 | | 0.0062 | 0.8339 | |
GDMTH | $/kWh Intermedio | 0.1809 | | 0.0065 | | 0.0062 | 1.4626 | |
| $/kWh Punta | 0.1809 | | 0.0065 | | 0.0062 | 1.6439 | |
| $/kW | | 94.64 | | | | | 421.46 |
| $/mes | | | | 2333.01 | | | |
| $/kWh Base | 0.1809 | | 0.0065 | | 0.0062 | 0.8625 | |
DIST | $/kWh Intermedio | 0.1809 | | 0.0065 | | 0.0062 | 1.4025 | |
| $/kWh Punta | 0.1809 | | 0.0065 | | 0.0062 | 1.6679 | |
| $/kW | | | | | | | 431.76 |
| $/mes | | | | 2333.01 | | | |
| $/kWh Base | 0.0794 | | 0.0065 | | 0.0062 | 0.7458 | |
DIT | $/kWh Intermedio | 0.0794 | | 0.0065 | | 0.0062 | 1.3113 | |
| $/kWh Punta | 0.0794 | | 0.0065 | | 0.0062 | 1.4579 | |
| $/kW | | | | | | | 421.37 |
Categorías | Tarifas Reguladas 2025 | Cargos variables | enero-25 | |||||
Transmisión | Distribución | Operación del CENACE | Operación del Suministrador Básico | Servicios conexos no MEM | Energía | Capacidad | ||
Categoría tarifaria | Unidades | |||||||
DB1 | $/mes | | | | 72.64 | | | |
| $/kWh | 0.1809 | 1.4078 | 0.0065 | | 0.0062 | 0.800 | 0.525 |
DB2 | $/mes | | | | 72.64 | | | |
| $/kWh | 0.1809 | 1.2476 | 0.0065 | | 0.0062 | 0.787 | 0.523 |
PDBT | $/mes | | | | 72.64 | | | |
| $/kWh | 0.1809 | 1.3317 | 0.0065 | | 0.0062 | 1.334 | 1.001 |
| $/mes | | | | 726.37 | | | |
GDBT | $/kWh | 0.1809 | | 0.0065 | | 0.0062 | 1.500 | |
| $/kW | | 357.81 | | | | | 326.70 |
RABT | $/mes | | | | 72.64 | | | |
| $/kWh | 0.1809 | 1.3317 | 0.0065 | | 0.0062 | 0.787 | 0.604 |
| $/mes | | | | 726.37 | | | |
RAMT | $/kWh | 0.1809 | | 0.0065 | | 0.0062 | 0.756 | |
| $/kW | | 76.22 | | | | | 165.68 |
APBT | $/mes | | | | 72.64 | | | |
| $/kWh | 0.1809 | 1.3317 | 0.0065 | | 0.0062 | 1.344 | 1.575 |
| $/mes | | | | 726.37 | | | |
APMT | $/kWh | 0.1809 | | 0.0065 | | 0.0062 | 1.128 | 1.248 |
| $/kW | | 76.22 | | | | | |
| $/mes | | | | 726.37 | | | |
GDMTO | $/kWh | 0.1809 | | 0.0065 | | 0.0062 | 1.126 | |
| $/kW | | 76.22 | | | | | 334.77 |
| $/mes | | | | 726.37 | | | |
| $/kWh Base | 0.1809 | | 0.0065 | | 0.0062 | 0.8897 | |
GDMTH | $/kWh Intermedio | 0.1809 | | 0.0065 | | 0.0062 | 1.5381 | |
| $/kWh Punta | 0.1809 | | 0.0065 | | 0.0062 | 1.8355 | |
| $/kW | | 76.22 | | | | | 431.76 |
| $/mes | | | | 2179.12 | | | |
| $/kWh Base | 0.1809 | | 0.0065 | | 0.0062 | 0.8363 | |
DIST | $/kWh Intermedio | 0.1809 | | 0.0065 | | 0.0062 | 1.4690 | |
| $/kWh Punta | 0.1809 | | 0.0065 | | 0.0062 | 1.7578 | |
| $/kW | | | | | | | 431.76 |
| $/mes | | | | 2179.12 | | | |
| $/kWh Base | 0.0794 | | 0.0065 | | 0.0062 | 0.8397 | |
DIT | $/kWh Intermedio | 0.0794 | | 0.0065 | | 0.0062 | 1.4632 | |
| $/kWh Punta | 0.0794 | | 0.0065 | | 0.0062 | 1.6952 | |
| $/kW | | | | | | | 431.76 |
Categorías | Tarifas Reguladas 2025 | Cargos variables | enero-25 | |||||
Transmisión | Distribución | Operación del CENACE | Operación del Suministrador Básico | Servicios conexos no MEM | Energía | Capacidad | ||
Categoría tarifaria | Unidades | |||||||
DB1 | $/mes | | | | 47.45 | | | |
| $/kWh | 0.1809 | 1.6259 | 0.0065 | | 0.0062 | 0.814 | 0.527 |
DB2 | $/mes | | | | 47.45 | | | |
| $/kWh | 0.1809 | 1.3967 | 0.0065 | | 0.0062 | 0.819 | 0.524 |
PDBT | $/mes | | | | 47.45 | | | |
| $/kWh | 0.1809 | 1.3292 | 0.0065 | | 0.0062 | 1.519 | 0.962 |
| $/mes | | | | 474.54 | | | |
GDBT | $/kWh | 0.1809 | | 0.0065 | | 0.0062 | 1.240 | |
| $/kW | | 526.33 | | | | | 242.70 |
RABT | $/mes | | | | 47.45 | | | |
| $/kWh | 0.1809 | 1.3292 | 0.0065 | | 0.0062 | 0.809 | 0.606 |
| $/mes | | | | 474.54 | | | |
RAMT | $/kWh | 0.1809 | | 0.0065 | | 0.0062 | 0.773 | |
| $/kW | | 211.58 | | | | | 165.68 |
APBT | $/mes | | | | 47.45 | | | |
| $/kWh | 0.1809 | 1.3292 | 0.0065 | | 0.0062 | 1.484 | 1.579 |
| $/mes | | | | 474.54 | | | |
APMT | $/kWh | 0.1809 | | 0.0065 | | 0.0062 | 1.232 | 1.235 |
| $/kW | | 211.58 | | | | | |
| $/mes | | | | 474.54 | | | |
GDMTO | $/kWh | 0.1809 | | 0.0065 | | 0.0062 | 1.214 | |
| $/kW | | 211.58 | | | | | 312.82 |
| $/mes | | | | 474.54 | | | |
| $/kWh Base | 0.1809 | | 0.0065 | | 0.0062 | 0.7902 | |
GDMTH | $/kWh Intermedio | 0.1809 | | 0.0065 | | 0.0062 | 1.5480 | |
| $/kWh Punta | 0.1809 | | 0.0065 | | 0.0062 | 1.7647 | |
| $/kW | | 211.58 | | | | | 386.86 |
| $/mes | | | | 1423.62 | | | |
| $/kWh Base | 0.1809 | | 0.0065 | | 0.0062 | 0.8610 | |
DIST | $/kWh Intermedio | 0.1809 | | 0.0065 | | 0.0062 | 1.6591 | |
| $/kWh Punta | 0.1809 | | 0.0065 | | 0.0062 | 1.8910 | |
| $/kW | | | | | | | 431.76 |
| $/mes | | | | 1423.62 | | | |
| $/kWh Base | 0.0794 | | 0.0065 | | 0.0062 | 0.9513 | |
DIT | $/kWh Intermedio | 0.0794 | | 0.0065 | | 0.0062 | 1.6707 | |
| $/kWh Punta | 0.0794 | | 0.0065 | | 0.0062 | 1.9835 | |
| $/kW | | | | | | | 431.76 |
Categorías | Tarifas Reguladas 2025 | Cargos variables | enero-25 | |||||
Transmisión | Distribución | Operación del CENACE | Operación del Suministrador Básico | Servicios conexos no MEM | Energía | Capacidad | ||
Categoría tarifaria | Unidades | |||||||
DB1 | $/mes | | | | 42.16 | | | |
| $/kWh | 0.1809 | 1.0664 | 0.0065 | | 0.0062 | 0.872 | 0.529 |
DB2 | $/mes | | | | 42.16 | | | |
| $/kWh | 0.1809 | 0.8810 | 0.0065 | | 0.0062 | 0.863 | 0.527 |
PDBT | $/mes | | | | 42.16 | | | |
| $/kWh | 0.1809 | 1.0240 | 0.0065 | | 0.0062 | 1.963 | 1.050 |
| $/mes | | | | 421.57 | | | |
GDBT | $/kWh | 0.1809 | | 0.0065 | | 0.0062 | 2.034 | |
| $/kW | | 309.09 | | | | | 326.70 |
RABT | $/mes | | | | 42.16 | | | |
| $/kWh | 0.1809 | 1.0240 | 0.0065 | | 0.0062 | 0.863 | 0.609 |
| $/mes | | | | 421.57 | | | |
RAMT | $/kWh | 0.1809 | | 0.0065 | | 0.0062 | 0.818 | |
| $/kW | | 94.61 | | | | | 165.68 |
APBT | $/mes | | | | 42.16 | | | |
| $/kWh | 0.1809 | 1.0240 | 0.0065 | | 0.0062 | 1.709 | 1.587 |
| $/mes | | | | 421.57 | | | |
APMT | $/kWh | 0.1809 | | 0.0065 | | 0.0062 | 1.401 | 1.236 |
| $/kW | | 94.61 | | | | | |
| $/mes | | | | 421.57 | | | |
GDMTO | $/kWh | 0.1809 | | 0.0065 | | 0.0062 | 1.656 | |
| $/kW | | 94.61 | | | | | 356.09 |
| $/mes | | | | 421.57 | | | |
| $/kWh Base | 0.1809 | | 0.0065 | | 0.0062 | 1.1180 | |
GDMTH | $/kWh Intermedio | 0.1809 | | 0.0065 | | 0.0062 | 2.0251 | |
| $/kWh Punta | 0.1809 | | 0.0065 | | 0.0062 | 2.2839 | |
| $/kW | | 94.61 | | | | | 421.46 |
| $/mes | | | | 1264.70 | | | |
| $/kWh Base | 0.1809 | | 0.0065 | | 0.0062 | 0.9985 | |
DIST | $/kWh Intermedio | 0.1809 | | 0.0065 | | 0.0062 | 1.8514 | |
| $/kWh Punta | 0.1809 | | 0.0065 | | 0.0062 | 2.0402 | |
| $/kW | | | | | | | 416.88 |
| $/mes | | | | 1264.70 | | | |
| $/kWh Base | 0.0794 | | 0.0065 | | 0.0062 | 0.9824 | |
DIT | $/kWh Intermedio | 0.0794 | | 0.0065 | | 0.0062 | 1.8299 | |
| $/kWh Punta | 0.0794 | | 0.0065 | | 0.0062 | 1.9711 | |
| $/kW | | | | | | | 412.22 |
Categorías | Tarifas Reguladas 2025 | Cargos variables | enero-25 | |||||
Transmisión | Distribución | Operación del CENACE | Operación del Suministrador Básico | Servicios conexos no MEM | Energía | Capacidad | ||
Categoría tarifaria | Unidades | |||||||
DB1 | $/mes | | | | 40.11 | | | |
| $/kWh | 0.1809 | 1.4207 | 0.0065 | | 0.0062 | 0.832 | 0.518 |
DB2 | $/mes | | | | 40.11 | | | |
| $/kWh | 0.1809 | 1.2180 | 0.0065 | | 0.0062 | 0.825 | 0.515 |
PDBT | $/mes | | | | 40.11 | | | |
| $/kWh | 0.1809 | 1.1583 | 0.0065 | | 0.0062 | 1.654 | 1.024 |
| $/mes | | | | 401.12 | | | |
GDBT | $/kWh | 0.1809 | | 0.0065 | | 0.0062 | 1.396 | |
| $/kW | | 459.11 | | | | | 266.88 |
RABT | $/mes | | | | 40.11 | | | |
| $/kWh | 0.1809 | 1.1583 | 0.0065 | | 0.0062 | 0.820 | 0.595 |
| $/mes | | | | 401.12 | | | |
RAMT | $/kWh | 0.1809 | | 0.0065 | | 0.0062 | 0.787 | |
| $/kW | | 147.44 | | | | | 165.68 |
APBT | $/mes | | | | 40.11 | | | |
| $/kWh | 0.1809 | 1.1583 | 0.0065 | | 0.0062 | 1.546 | 1.550 |
| $/mes | | | | 401.12 | | | |
APMT | $/kWh | 0.1809 | | 0.0065 | | 0.0062 | 1.314 | 1.254 |
| $/kW | | 147.44 | | | | | |
| $/mes | | | | 401.12 | | | |
GDMTO | $/kWh | 0.1809 | | 0.0065 | | 0.0062 | 1.165 | |
| $/kW | | 147.44 | | | | | 278.03 |
| $/mes | | | | 401.12 | | | |
| $/kWh Base | 0.1809 | | 0.0065 | | 0.0062 | 0.8781 | |
GDMTH | $/kWh Intermedio | 0.1809 | | 0.0065 | | 0.0062 | 1.6780 | |
| $/kWh Punta | 0.1809 | | 0.0065 | | 0.0062 | 1.9075 | |
| $/kW | | 147.44 | | | | | 370.72 |
| $/mes | | | | 1203.37 | | | |
| $/kWh Base | 0.1809 | | 0.0065 | | 0.0062 | 0.9138 | |
DIST | $/kWh Intermedio | 0.1809 | | 0.0065 | | 0.0062 | 1.6902 | |
| $/kWh Punta | 0.1809 | | 0.0065 | | 0.0062 | 1.9848 | |
| $/kW | | | | | | | 421.46 |
| $/mes | | | | 1203.37 | | | |
| $/kWh Base | 0.0794 | | 0.0065 | | 0.0062 | 0.7732 | |
DIT | $/kWh Intermedio | 0.0794 | | 0.0065 | | 0.0062 | 1.4842 | |
| $/kWh Punta | 0.0794 | | 0.0065 | | 0.0062 | 1.6529 | |
| $/kW | | | | | | | 374.28 |
Categorías | Tarifas Reguladas 2025 | Cargos variables | enero-25 | |||||
Transmisión | Distribución | Operación del CENACE | Operación del Suministrador Básico | Servicios conexos no MEM | Energía | Capacidad | ||
Categoría tarifaria | Unidades | |||||||
DB1 | $/mes | | | | 46.68 | | | |
| $/kWh | 0.1809 | 0.7937 | 0.0065 | | 0.0062 | 0.856 | 0.593 |
DB2 | $/mes | | | | 46.68 | | | |
| $/kWh | 0.1809 | 0.6807 | 0.0065 | | 0.0062 | 0.854 | 0.590 |
PDBT | $/mes | | | | 46.68 | | | |
| $/kWh | 0.1809 | 0.6469 | 0.0065 | | 0.0062 | 1.865 | 1.216 |
| $/mes | | | | 466.83 | | | |
GDBT | $/kWh | 0.1809 | | 0.0065 | | 0.0062 | 1.953 | |
| $/kW | | 256.43 | | | | | 334.71 |
RABT | $/mes | | | | 46.68 | | | |
| $/kWh | 0.1809 | 0.6469 | 0.0065 | | 0.0062 | 0.840 | 0.688 |
| $/mes | | | | 466.83 | | | |
RAMT | $/kWh | 0.1809 | | 0.0065 | | 0.0062 | 0.777 | |
| $/kW | | 64.12 | | | | | 165.68 |
APBT | $/mes | | | | 46.68 | | | |
| $/kWh | 0.1809 | 0.6469 | 0.0065 | | 0.0062 | 1.686 | 1.792 |
| $/mes | | | | 466.83 | | | |
APMT | $/kWh | 0.1809 | | 0.0065 | | 0.0062 | 1.247 | 1.212 |
| $/kW | | 64.12 | | | | | |
| $/mes | | | | 466.83 | | | |
GDMTO | $/kWh | 0.1809 | | 0.0065 | | 0.0062 | 1.505 | |
| $/kW | | 64.12 | | | | | 373.75 |
| $/mes | | | | 466.83 | | | |
| $/kWh Base | 0.1809 | | 0.0065 | | 0.0062 | 0.9826 | |
GDMTH | $/kWh Intermedio | 0.1809 | | 0.0065 | | 0.0062 | 1.7587 | |
| $/kWh Punta | 0.1809 | | 0.0065 | | 0.0062 | 2.0888 | |
| $/kW | | 64.12 | | | | | 431.76 |
| $/mes | | | | 1400.49 | | | |
| $/kWh Base | 0.1809 | | 0.0065 | | 0.0062 | 1.0039 | |
DIST | $/kWh Intermedio | 0.1809 | | 0.0065 | | 0.0062 | 1.8722 | |
| $/kWh Punta | 0.1809 | | 0.0065 | | 0.0062 | 2.1446 | |
| $/kW | | | | | | | 431.76 |
| $/mes | | | | 1400.49 | | | |
| $/kWh Base | 0.0794 | | 0.0065 | | 0.0062 | 1.0039 | |
DIT | $/kWh Intermedio | 0.0794 | | 0.0065 | | 0.0062 | 1.8837 | |
| $/kWh Punta | 0.0794 | | 0.0065 | | 0.0062 | 2.1058 | |
| $/kW | | | | | | | 431.76 |
Categorías | Tarifas Reguladas 2025 | Cargos variables | enero-25 | |||||
Transmisión | Distribución | Operación del CENACE | Operación del Suministrador Básico | Servicios conexos no MEM | Energía | Capacidad | ||
Categoría tarifaria | Unidades | |||||||
DB1 | $/mes | | | | 56.36 | | | |
| $/kWh | 0.1809 | 1.0192 | 0.0065 | | 0.0062 | 0.892 | 0.703 |
DB2 | $/mes | | | | 56.36 | | | |
| $/kWh | 0.1809 | 0.8746 | 0.0065 | | 0.0062 | 0.891 | 0.699 |
PDBT | $/mes | | | | 56.36 | | | |
| $/kWh | 0.1809 | 0.8312 | 0.0065 | | 0.0062 | 1.732 | 1.189 |
| $/mes | | | | 563.57 | | | |
GDBT | $/kWh | 0.1809 | | 0.0065 | | 0.0062 | 2.086 | |
| $/kW | | 329.17 | | | | | 321.12 |
RABT | $/mes | | | | 56.36 | | | |
| $/kWh | 0.1809 | 0.8312 | 0.0065 | | 0.0062 | 0.877 | 0.823 |
| $/mes | | | | 563.57 | | | |
RAMT | $/kWh | 0.1809 | | 0.0065 | | 0.0062 | 0.776 | |
| $/kW | | 91.12 | | | | | 165.68 |
APBT | $/mes | | | | 56.36 | | | |
| $/kWh | 0.1809 | 0.8312 | 0.0065 | | 0.0062 | 1.942 | 2.144 |
| $/mes | | | | 563.57 | | | |
APMT | $/kWh | 0.1809 | | 0.0065 | | 0.0062 | 1.178 | 1.181 |
| $/kW | | 91.12 | | | | | |
| $/mes | | | | 563.57 | | | |
GDMTO | $/kWh | 0.1809 | | 0.0065 | | 0.0062 | 1.466 | |
| $/kW | | 91.12 | | | | | 366.47 |
| $/mes | | | | 563.57 | | | |
| $/kWh Base | 0.1809 | | 0.0065 | | 0.0062 | 0.9794 | |
GDMTH | $/kWh Intermedio | 0.1809 | | 0.0065 | | 0.0062 | 1.7451 | |
| $/kWh Punta | 0.1809 | | 0.0065 | | 0.0062 | 2.0753 | |
| $/kW | | 91.12 | | | | | 431.76 |
| $/mes | | | | 1690.72 | | | |
| $/kWh Base | 0.1809 | | 0.0065 | | 0.0062 | 0.6812 | |
DIST | $/kWh Intermedio | 0.1809 | | 0.0065 | | 0.0062 | 1.3375 | |
| $/kWh Punta | 0.1809 | | 0.0065 | | 0.0062 | 1.5325 | |
| $/kW | | | | | | | 421.46 |
| $/mes | | | | 1690.72 | | | |
| $/kWh Base | 0.0794 | | 0.0065 | | 0.0062 | 0.6112 | |
DIT | $/kWh Intermedio | 0.0794 | | 0.0065 | | 0.0062 | 1.1974 | |
| $/kWh Punta | 0.0794 | | 0.0065 | | 0.0062 | 1.3448 | |
| $/kW | | | | | | | 421.46 |
Categorías | Tarifas Reguladas 2025 | Cargos variables | enero-25 | |||||
Transmisión | Distribución | Operación del CENACE | Operación del Suministrador Básico | Servicios conexos no MEM | Energía | Capacidad | ||
Categoría tarifaria | Unidades | |||||||
DB1 | $/mes | | | | 44.88 | | | |
| $/kWh | 0.1809 | 0.9826 | 0.0065 | | 0.0062 | 0.903 | 0.724 |
DB2 | $/mes | | | | 44.88 | | | |
| $/kWh | 0.1809 | 0.8420 | 0.0065 | | 0.0062 | 0.902 | 0.720 |
PDBT | $/mes | | | | 44.88 | | | |
| $/kWh | 0.1809 | 0.8010 | 0.0065 | | 0.0062 | 1.766 | 1.208 |
| $/mes | | | | 448.77 | | | |
GDBT | $/kWh | 0.1809 | | 0.0065 | | 0.0062 | 2.199 | |
| $/kW | | 317.32 | | | | | 326.70 |
RABT | $/mes | | | | 44.88 | | | |
| $/kWh | 0.1809 | 0.8010 | 0.0065 | | 0.0062 | 0.887 | 0.849 |
| $/mes | | | | 448.77 | | | |
RAMT | $/kWh | 0.1809 | | 0.0065 | | 0.0062 | 0.779 | |
| $/kW | | 71.18 | | | | | 165.68 |
APBT | $/mes | | | | 44.88 | | | |
| $/kWh | 0.1809 | 0.8010 | 0.0065 | | 0.0062 | 2.018 | 2.213 |
| $/mes | | | | 448.77 | | | |
APMT | $/kWh | 0.1809 | | 0.0065 | | 0.0062 | 1.258 | 1.216 |
| $/kW | | 71.18 | | | | | |
| $/mes | | | | 448.77 | | | |
GDMTO | $/kWh | 0.1809 | | 0.0065 | | 0.0062 | 1.520 | |
| $/kW | | 71.18 | | | | | 375.46 |
| $/mes | | | | 448.77 | | | |
| $/kWh Base | 0.1809 | | 0.0065 | | 0.0062 | 0.9912 | |
GDMTH | $/kWh Intermedio | 0.1809 | | 0.0065 | | 0.0062 | 1.7702 | |
| $/kWh Punta | 0.1809 | | 0.0065 | | 0.0062 | 2.1054 | |
| $/kW | | 71.18 | | | | | 431.76 |
| $/mes | | | | 1346.31 | | | |
| $/kWh Base | 0.1809 | | 0.0065 | | 0.0062 | 0.9906 | |
DIST | $/kWh Intermedio | 0.1809 | | 0.0065 | | 0.0062 | 1.7619 | |
| $/kWh Punta | 0.1809 | | 0.0065 | | 0.0062 | 2.1041 | |
| $/kW | | | | | | | 431.76 |
| $/mes | | | | 1346.31 | | | |
| $/kWh Base | 0.0794 | | 0.0065 | | 0.0062 | 1.0082 | |
DIT | $/kWh Intermedio | 0.0794 | | 0.0065 | | 0.0062 | 1.8794 | |
| $/kWh Punta | 0.0794 | | 0.0065 | | 0.0062 | 2.1137 | |
| $/kW | | | | | | | 431.76 |